Case · 2024
Leiden: a construction site with no grid connection

What changed
- 42% cheaper than diesel
- Close to 100% CO₂ reduction
- Permit approved
Situation
What we did
Understand
Simulated the site's energy demand across the working day.
Decide
Chose a 15 kVA hybrid set-up: battery, foldable solar and an HVO backup generator. At the time we also supplied the equipment; today we advise on sizing and supplier choice only.
Implement
Supported the permit application; the municipality of Leiden approved the system.
Manage
Monitored the system live and reported monthly.
What it taught us
Sized to the real load, the right set-up is often smaller and simpler than a worst-case design, and a municipality says yes to a plan that is properly argued.