Flex Scan

Know where you stand, and what you can do, in three weeks

A fixed-scope scan of your grid position and your options, with numbers you can take to your management.
Outcome
Your real grid position and your three most viable routes, each with a number against it.
Duration
About 3 weeks
We start from our own tools and from more than 1,500 projects modelled in our Decision Tool, so our answers come in weeks and are precise. You buy the answer, not the software.
You receive
Decision memo, options model, management presentation.
Fee
From €4,000 excl. VAT, fixed fee agreed before we start.

When to use it

  • Your expansion is blocked

  • Your charging plan has stalled

  • You received a letter from the grid operator

  • A flex contract is on the table

What we look at

  • Contracted versus actual capacity: how much of your connection you really use, and when.
  • Queue and congestion status: where you stand with your grid operator, and how long the wait is.
  • Flex contract eligibility: which flex contracts your site qualifies for.
  • Your load profile: when your peaks happen, and which of them can move.
  • Your growth plans: what you need, and by when.

What you get

  1. Decision memo

    Up to 20 pages with three costed routes.

  2. Options model

    The numbers behind each route, for your own scenarios.

  3. Management presentation

    We present the findings to your management.

Illustrative example. Not a client.

Flex Scan · Decision memo · Summary

Site:
distribution centre, contracted capacity 1,000 kW, grid operator Liander, congestion area: demand.
Question:
can the site add 800 kW for electric trucks and a new cold store by Q3 2027?
Our answer:
yes, but not with a regular capacity increase. The queue for extra transport capacity in this area runs beyond 2030.
RouteExtra capacityAvailable fromRelative costMain risk
A. Time-based capacity limitation contract plus smart charging
+600 kW
Q2 2027
Low
Night-time charging window must hold
B. Route A plus 1.5 MWh battery as-a-service
+900 kW
Q3 2027
Medium
Contract term vs battery term
C. Wait for reinforcement
+800 kW
2031 or later
None
Growth on hold for 4+ years

Recommendation: Route B. It is the only route that covers the full 800 kW before the deadline, and the battery can earn part of its cost when the site doesn't need it.

Page 1 of a Flex Scan decision memo. The full memo (up to 20 pages) covers the load profile, contract terms, the numbers behind each route and what to ask the grid operator.

What we need from you

  • Connection data
  • Meter data, if available
  • Your growth plans

What happens next

Most clients continue with a business case, a portfolio programme or implementation support. The Flex-E subsidy may cover the scan. Check Flex-E

Start your Flex Scan

About three weeks from data to decision memo.

Bart LouwerenburgChief commercial officer. Your request goes straight to him.

Your choice about cookies

We measure visits without cookies and anonymously, to see which pages lead to a request. With your permission PostHog also follows your visit with a cookie across pages and days, and we may share your visit with Google Ads and LinkedIn to measure our ads. PostHog keeps no IP addresses and never records what you type in a form.

Read about cookies in the privacy policy